Colbert Ash Stack Closure Complete

by Staff
0 comment

COLBERT COUNTY-TVA recently completed a $16 million project to close the dry ash stack at the now-retired Colbert Fossil Plant in Colbert County, Ala. Started in the summer of 2015, this 67-acre project involved the installation of over 2.8 million square feet of plastic liner, 255,000 tons of soil (enough to cover the site to a depth of 18 inches) and 2.7 million square feet of sod.

colbert-aerial-10-2016-810x648

“By following TVA project management procedures, the joint project team worked collectively within their disciplines by incorporating lessons learned and other closure experiences to complete the Stack 5 project under budget, ahead of schedule and with no safety instances,” says

Kris Johnson

Kris Johnson

, general manager, Civil Project Management.

When the decision was made to shut down the generating facility, the team recognized an opportunity to accelerate closure of Stack 5 by more than a year by shifting the last few months of ash placement to an adjacent Pond 4. Using lessons learned from a pond closure at Widows Creek, the team recommended eliminating a 6-inch topsoil layer and placing sod instead, which saved two months of construction time andmore than $1 million.

A cloth layer above the plastic liner keeps rainwater off the stack. This advanced, highly engineered cover system will be monitored by TVA for the next 30 years. Groundwater also will be monitored and results reported to the Alabama Department of Environmental Management.

The scenic quality of the area is much improved by the closure. Large herds of deer and flocks of wild turkeys, along with other wildlife, have already made this area their home.

Media Release/Scott Fiedler
Public Relations & Corp. Info.
Tennessee Valley Authority

 

Related Posts

Leave a Reply

[script_13]

This site uses Akismet to reduce spam. Learn how your comment data is processed.